Slab prep
Forms for the concrete slab are placed. The grade away from the street made the slab about 3 feet above ground level at the back of the house.
Frame
House just being framed up
Fireplace rough-in
The fireplace is a wood-burning fireplace but is fitted with natural gas, and can receive a fireplace insert that uses the natural gas.
Slab prep
Forms for the concrete slab are placed. The grade away from the street made the slab about 3 feet above ground level at the back of the house.
Bay Window
A bay window was added for the master bedroom, which faces the conservation area behind the house.
Stonework
Austin stone (a white limestone) was added to the front finish. The same stone was used for the fireplace.
Fireplace
The fireplace after insulation and drywall
Ceramic tile floor
A ceramic tile floor was used for high durability on the main floor. Stairs and upstairs are carpeted.
Workbench
I built a work area in the corner of the garage.
Finished house
House as finished. We've started on doing some landscaping but that will be a multiyear project.
Views
Views from the kitchen/living room.
Views
Views from the kitchen/living room.
Penntek in the garage
We added a floor coating in the garage called Penntek. Makes the garage brighter and we don't need to worry about spills.